Goal
Energetic utilization of refinery residues and secure supply of the entire refinery
Solution
Construction of the power plant under the finance lease model, operation via management contract
- Financing, construction and operational management of the refinery power plant
- Ongoing modernization and optimization
Results
Further reduction of CO2 emissions by up to 40% compared to current levels with the implementation of the current fuel flexibilization project
Impact
Increased efficiency, cost reduction, fuel flexibilization